Here's the project timeline for Bloomington, IN's Indiana Avenue Safety Improvements:
- Informational Neighborhood Letter
Note: Letters mailed to businesses and residents within 300ft of the project area - First Public Meeting: Project Scope and Objectives - Tuesday, June 11 at 5:30pm at the Sample Gates
- Second Public Meeting: Preliminary Design Review and Feedback - Tuesday, July 16 at 5:30pm
Note: Rain Date is scheduled for Wednesday, July 17 at 5:30pm - Third Public Meeting: Further Design Review and Feedback - Tuesday, August 13 at 5:30pm
Note: Rain Date is scheduled for Wednesday, August 14 at 5:30pm - Project Scope and Objectives Survey Period: Open until noon on Friday, June 28th.
- Bicycle and Pedestrian Safety Commission Review: Fall, 2024
- Traffic Commission Review: Fall, 2024
- Installation: Spring - Summer, 2025
Here's the project timeline for W 3rd Street Maintenance Project (Franklin to Patterson)
- Bids to go out June 24, 2024
- Bid awarded at the end of July 2024
- Construction will start in 2024 on portions of this project.
Wouldn't it be nice if the process for safety improvements was as simple as the process for street maintenance?